Projects

2015 Nagoya port outport area
break water (Nabetatei) repair work


DATA

This project was to prepare for the expected big earth quake and concerned tsunami after the earthquake.
Kojimagumi was a subcontractor of Wakachiku Construction., Co., Ltd.
Existing breakwater had sand and rubble for filling. By replacing them with concrete, it added heaviness and more firmness to be able to endure against disaster.
Project 2015 Nagoya port outport area
break water (Nabetatei) repair work
Period December, 2015 - October, 2016
Client Chubu regional development bureau of the Ministry of Land, Infrastructure, Transport and Tourism
Location Nagoya port break water (Nabetatei)
Outline Removing rubble/filling and improving filling