Tuas container terminal construction project(TTP1)


DATA

They are relocating the container terminal function from the center of Singapore to Tuas district in the western part of Singapore. Now our 3 grab dredgers, GOSHO, 661 RYOSEI MARU, and 381 RYOSEI MARU, are operating for channel, basin, and trench dredging.
Project Singapore, Tuas container terminal construction project(TTP1)
Period March, 2015 - June, 2019
Client Maritime and Port Authority of Singapore
Contractor JV of Dredging International Asia Pacific Pte Ltd. and DAELIM Co., Ltd.
Outline We operated to accomplish a total grab dredging volume of 34 million m3.
Detail 381 RYOSEIMARU
Period: Jul 2015 - Jan 2019
Dredging hours: 23,011h
Dredged volume: 5,195,574m3

661 RYOSEIMARU
Period: Apr 2016 - May 2020
Dredging hours: 26,855h
Dredged volume: 13,330,097m3

GOSHO
Period: Apr 2016 - Apr 2019
Dredging hours: 18,083h
Dredged volume: 15,544,300m3