Projects

Saudi Arabia
King Fahd industrial port dredging


DATA

The project site was located at King Fahd industrial port in Yanbu on the east coast of the Red Sea in the eastern Saudi Arabia. We operated with GOSHO'S 136 m3 and 200 m3 grab bucket. Most of the dredged soil was hard coral reef. Harsh weather condition with strong wind and swell gave us a hard time in channel dredging.
Project Saudi Arabia King Fahd industrial port dredging
Period February, 2011 - November, 2012
Client Ports authority of Kingdom of Saudi Arabia
Contractor China Harbour Engineering Company Ltd.
Outline Channel/basin deepening for larger vessel's safe navigation. Total dredging volume, 4 million m3.