Comprehensive flood control for specified river
(Grant, disaster control safety) (Phase 2)


DATA

We dredged the sediment upstream starting from 300m downstream area of Jyunrei bridge in Gojogawa River.
Dredging the river bottom can make the water level lower, then flood starts flowing downstream safe.
Dredged soil was transported to 300m downstream dump site of Jyunrei bridge by water and it will be utilized as reclamation material after dewatered for public facility.
Project Comprehensive flood control for specified river (Grant, disaster control safety) (Phase 2)
Period February, 2017 - May, 2017
Client Kawamura sangyosho Co., Ltd. (Owari Construction office of Aichi prefecture)
Outline Construction length 360.0m V=18,900m3
Backhoe dredging (Backhoe dredger 2.0m3 class×1)
Transport by barge (Barge 60m3 class×2, push boat 400ps class×1)
Backhoe unloading (Backhoe 0.8m3 class×1, wheel loader 1.0m3 class×1)